SIPCO aim for an 10 weeks typical lead-time from order to site delivery - see below. This is based on 100% information availability from the client and architect:
WEEK 1 |
- Receive and accept SIPCO estimate |
WEEK 2 |
- SIPCO invoice for 10% to cover design fees - Commission engineers report |
WEEK 4 |
- Receive engineers design, review estimate and issue fixed price, Any savings passed back to client |
WEEK 5 |
- Commence SIP design |
WEEK 7 |
- Receive signed approval drawings - Forward SIP design to client/architect for signature |
WEEK 8 |
- Start manufacturing process |
WEEK 10 |
- Delivery |